Evaluating the State of Earned Value Management Research

 

and Finding Paths Forward

 

FEATURED PAPER

By Andrew J. Grandage, PhD

North Carolina, USA


Abstract

The Earned Value Management (EVM) literature consists of an extensive and diverse collection of practitioner writings, governmental reports, and peer-reviewed journal articles. However, relatively few attempts have been made to take stock of this vast literature and provide direction for future research. This paper provides a comprehensive review of peer-reviewed articles on EVM published from 2015 to 2025. The analysis of 227 articles summarizes the industries that have been studied, research methods and data sources used, the contributions of the articles, and gaps in the literature. The paper concludes by inviting practitioners to help shape the future of EVM research through a ranked choice voting process designed to establish research priorities.

Introduction

Over the last several decades, the field of project management has experienced a proliferation of standards, guidelines, and certifications intended to establish best practices and qualifications for project professionals. The contents of these standards and guidelines are consequential because organizations often develop their procedures in accordance with them, while certifications can serve as a gatekeeping function by establishing qualifications for entry into and advancement within the profession. Therefore, project management research is needed to ensure that the field’s increasingly extensive body of standards and guidelines is grounded in evidence. Furthermore, such research should aim to do more than justify existing practices by striving to improve their use and meeting the evolving needs of practice.

The purpose of this paper is to evaluate the state of Earned Value Management (EVM) research and begin a conversation of how future research can better support professional practice. Given the central role of EVM in project management and its increasingly vast body of research, there is an ongoing need to take stock of the literature, bring greater organization to what is known, and identify the areas in which future research can provide the greatest value. This study analyzes 227 peer-reviewed papers that were published from 2015 to 2025.

Results demonstrate that EVM research has explored a variety of industries, but construction projects are by far the most commonly studied. The primary contributions of the papers focus on forecasting, project monitoring, and analyzing factors contributing to successful implementation. Yet, relatively few examine whether EVM improves project performance by demonstrating that use of it leads to better cost and/or schedule results. The studies utilize a variety of research methods and data sources, with some of the approaches being quite rigorous. However, many papers do not have adequate sample sizes that are necessary for proper statistical analysis, often utilizing a limited number of case studies.

At the outset, it is important to clarify the perspective this paper is written from. It is certainly not written from the point of view that practitioners need direction from academics. It is essentially the opposite. As an academic researcher, the author feels that the academic community needs direction from practitioners to conduct more impactful and engaged research. However, for this joint effort to be most productive, it is necessary to provide an up-to-date literature review as a reference point for where we are now.

The paper begins by briefly highlighting other key literature reviews on EVM. The following section explains the approach used to analyze the 227 peer-reviewed articles. Next, the results section summarizes the findings. The discussion section which follows focuses on current gaps in the literature. The paper concludes by issuing a call to practitioners to guide EVM research by participating in a ranked choice voting process to establish priorities.

More…

To read entire paper, click here

How to cite this paper: Grandage, A.J. (2026). Evaluating the State of Earned Value Management Research and Finding Paths Forward; PM World Journal, Vol. XV, Issue XI, November. Available online at https://pmworldjournal.com/wp-content/uploads/2026/11/pmwj170-Nov2026-Grandage-2027-State-of-EVM-Research.pdf


About the Author


Andrew J. Grandage, PhD

North Carolina, USA

 

Andrew J. Grandage, PhD, is an Associate Professor at Western Carolina University in Cullowhee, North Carolina. His research interests focus on public administration, specifically the nexus of performance management, budgeting, and project management. Recent publications include work on project management in U.S. state governments and capital planning at the local level. Andrew teaches courses on public administration, budgeting, and American government. He earned his PhD from The University of Georgia in Public Administration and Policy with a specialization in Public Budgeting and Financial Management. Prior to his academic career, Andrew worked as a financial analyst at Harris Corporation (now L3Harris Technologies) for several years. Prof Grandage can be contacted at agrandage@email.wcu.edu.