REPORT
By Dr Jouko Vaskimo
International Correspondent & Senior Contributing Editor
Espoo, Finland
INTRODUCTION
This roundup continues the coverage of Project Management Association Finland, PMI Finland Chapter and some of the key projects currently going on in Finland.
Association of Project Professionals Finland
Association of Project Professionals Finland (APPF), formerly referred to as Project Management Association Finland (PMAF), is a not-for-profit organization, and the International Project Management Association (IPMA) Member Association (MA) in Finland. Founded in 1978, APPF promotes the interaction, project-oriented thinking, and exchange and development of practical and theoretical knowledge among project management professionals with over 4000 individual and 200 organizational members.
APPF promotes the development and dissemination of project and project management knowledge. APPF members are able to enjoy information sharing, workgroups, development projects, project management forums, conferences and certification services APPF provides. APPF organizes two annual conferences: Projektipäivät in early November and 3PMO in early June. Please navigate to www.pry.fi/en , https://www.oppia.fi/events/3pmo2020/ and www.projektipaivat.fi for general information on APPF and its annual events.
PMI FINLAND CHAPTER
PMI Finland Chapter is a not-for-profit organization providing project practitioners in Finland continuous learning, networking and community support. The Chapter was founded in 2005. Today, with more than 400 members, the chapter is increasingly recognized as a community where its members can enhance their project management and leadership skills, as well as network with other project management professionals.
PMI Finland Chapter hosts a number of events such as Breakfast Round Tables, regular meetings taking place once a month in Helsinki and occasionally also in other locations. The chapter members have the opportunity to attend events for free or with a discount and the chapter sends its members a regular newsletter with localized content on project management. Additionally, the Chapter supports its members in their professional development and training.
PMI Chapter Finland organizes an annual conference in the spring, however, due to the COVID-19 pandemic the 2020 event was cancelled. Please navigate to www.pmifinland.org and www.conference.pmifinland.org for general information on the PMI Finland Chapter and its annual events
OLKILUOTO 3
The 1 600 MW Olkiluoto 3 nuclear power plant, originally contracted to be built by consortium comprising Areva and Siemens for Teollisuuden Voima (TVO) at Olkiluoto, Finland, is nearing completion. The plant was scheduled to be connected to the Finnish national power grid in November 2020, and commercial power generation was expected to commence in March 2021, however, according to the latest time schedule – released in late August 2020 – commercial power generation commences in February 2022. Nuclear fuel rods will be loaded into the reactor in March 2021, and the unit connected to the Finnish national power grid in October 2021.
Originally targeted for commercial power generation in June 2009, the power plant has been subject to a substantial number of challenges. In March 2018 an agreement was reached between TVO and Areva regarding the overruns in project budget and time schedule. According to TVO, Areva agreed to compensate 450 M€ assuming the power plant was fully operational by the end of 2019. If the plant was not fully operational at that time, Areva will compensate a further 400 M€. As part of the agreement, both contractual parties agreed to dispend any further judicial acts. It is unclear, whether Areva has already compensated, or will compensate the agreed 850 M€ in full.
Once completed, the 1 600 MW nuclear power station will be one of the largest in the world. TVO has been understandably disappointed about the fact that the plant is almost 200 % over original budget and 12 years behind the original time schedule.
The contract for building the Olkiluoto 3 power plant was signed in 2003 for 3 000 M€, and construction began in 2005, targeting completion in June 2009. Due to numerous challenges during the planning and construction phases, the target date has been pushed forward several times – almost thirteen years in total. The delays have pushed the total cost up to over 8 500 M€.
More…
To read entire report, click here
How to cite this report: Vaskimo, J. (2020). Finland Project Management Roundup, report, PM World Journal, Vol. IX, Issue XII, December. Available online at https://pmworldlibrary.net/wp-content/uploads/2020/12/pmwj100-dec2020-Vaskimo-Finland-Project-Management-Roundup-report.pdf
About the Author
Dr Jouko Vaskimo
Espoo, Finland
Jouko Vaskimo is an International Correspondent and Senior Contributing Editor for PM World in Finland. Jouko graduated M.Sc. (Tech.) from Helsinki University of Technology in 1992, and D.Sc. (Tech.) from Aalto University in 2016. He has held several project management related positions with increasing levels for responsibility. Jouko holds a number of professional certificates in the field of project management, such as the IPMA Level C (Project Manager), IPMA Level B (Senior Project Manager), PMP, PRINCE2 Foundation, and PRINCE2 Practitioner. Jouko is also a Certified Scrum Master and SAFe Agilist. Jouko is a member of the Project Management Association Finland, a founding member of PMI Finland Chapter, and the immediate past chairman of the Finnish IPMA Certification Body operating IPMA certification in Finland. Since October 2007, he has been heading the Finnish delegation to ISO/TC 258. Jouko resides in Espoo, Finland and can be best contacted at jouko.vaskimo@aalto.fi . For more information please navigate to www.linkedin.com/in/jouko-vaskimo-6285b51 .
To view other works by Jouko Vaskimo, visit his author showcase in the PM World Library at http://pmworldlibrary.net/authors/jouko-vaskimo/